by: John M. Hill
At 06:51 PM MST on 10 July, the temperature of the furnace reached 450
C after cooling through the annealing range of temperatures at a rate
of less than 3 degrees per day. The furnace control system has been
well-behaved and annealing has been quite peaceful. The oven pilots
are bored stiff, but they remain ever vigilant --- or at least as
vigilant as you can be at 2 AM. The glass is now quite rigid and
relatively stress free. The tension on the Inconel bands has been
reduced to a fraction of its original value since support against
hydrostatic forces is no longer needed. Our job now is to cool the
honeycomb blank from 450 C down to room temperature without damaging
it. Even though the cooling rate will increase to about 10 degrees per
day for a while, there are still two months of cooling left to go
before we get to open the furnace in September. Next week we will
apply the "hot flotation" pushers (counterbalanced levers) which
partially float the mirror and support it to protect against changes in
the shape of the hearth as the furnace cools.
LBT construction on Mt. Graham is going fairly well, we are presently
pouring concrete on the telescope pier at a level 56 feet above the
ground. The main concrete work on the telescope pier and the enclosure
ring wall should be complete by August. Then we start erecting the
steel frame of the fixed section of the enclosure. In the Project
Office, we are quite busy with the bidding of the main steel pieces of
the telescope structure.
Executive Summary:
The 8.4m mirror has cooled below 450 °C and
successfully completed the annealing phase.
